Sunday, September 27, 2015
Bathroom fittings and fixtures and Appliances.
![]() |
Master ensuite 1760 free standing bath |
![]() |
Mizu Drift floor mounted water outlet for freestanding batg |
LAUFEN Kartell round 420 basin for master ensuite |
![]() |
Milli Axon extended basin mixer (chrome) for master ensuites |
![]() |
Master ensuites toilet Fowler Seido icon series 2 |
![]() |
Methven kiri exposure shower head and rail for master ensuite |
![]() |
Methven kiri basin mixer for powder room, ES2,3,4 |
![]() |
Porcher Cygnet shower head and rail for powder room and ES 2,3,4, |
![]() |
Shower and Bath mixer for all rooms |
Powder room and ES 2,3,4 will have Ideal Standard Strada Rectangular basin undermount. I can't find the photo of it.
![]() |
ROCA Meridian back to wall toilet for powder room, ES 2,3,4 |
![]() |
Pantry's sink Clark Pete Evans 6610 |
![]() |
Kitchen, Pantry and Laundry's sink mixers. |
![]() |
Clark Pete Evans double undermount kitchen sink |
![]() |
SMEG linear cooktop with glass |
![]() |
Blum Aventos HK for cupboard above the fridge. |
![]() |
Blum Aventos HS up and over for 3 overhead cupboards in kitchen and 2 in Pantry |
![]() |
SMEG CK2000-76 undermount rangehood |
![]() |
SMEG Oven SF304x |
![]() |
Microwave Smeg SA37x |
Saturday, September 26, 2015
Stormwater drainage and pipes installed
Stormwater pipes have been installed after the strip footing is done.
Next thing will be the brickbase and supporting pillar.
Next thing will be the brickbase and supporting pillar.
Wednesday, September 23, 2015
One week after excavation,the strip footing is poured in one day. such a quick progress.
The neighbour complains about the timber fence at the rear is wobbling due to demolition and removing the root of the tree. We have to reassure them that we will fix the fence when we do our landscape and fence after the house is finished.
Site manager told me that the storm water drainage and brick pillar footing will be next.
Here are the photos of the strip footing.
The neighbour complains about the timber fence at the rear is wobbling due to demolition and removing the root of the tree. We have to reassure them that we will fix the fence when we do our landscape and fence after the house is finished.
Site manager told me that the storm water drainage and brick pillar footing will be next.
Here are the photos of the strip footing.
Reinforcing steel inside the strip footing |
Wednesday, September 16, 2015
Construction starts, Site excavation
Today is the 16 of September 2015, the site is excavated and start building. The Religious praying done before the site is excavated. Here are some pictures.
The house to be built is Metricon Bordeaux 50sq with slightly modification.
The house has 5 bedrooms, 5 bathrooms and double garage.
Excavator is ready |
Excavator is ready |
pre-start praying |